EVIDENTIARY THRESHOLD OF PROVING ACTUAL LOSS IN CONSTRUCTION ARBITRATION


In construction arbitration establishing a breach of contract or delay attributable to the employer is only the threshold inquiry and the main task lies on the actual proof of loss. A finding based on no evidence is perverse and is liable to be set aside on the ground of patent illegality as held by the Supreme Court in Ssangyong Engineering and Construction Company Limited v. National Highways Authority of India (NHAI), AIR OnLine 2019 SC 329.

The common claims which all contractors raise are compensation for the prolongation of plant and machinery, idling charges, site and head-office overheads, loss of profit, or loss of opportunity etc. However, the evidentiary threshold to win these claims in arbitration is extremely high. Courts have consistently affirmed that mere proof of breach or delay does not automatically entitle payment of  damages for these claims and the party claiming the same must prove with cogent and credible evidence. 


Under Sections 73 and 74 of the Contract Act, only the innocent party who actually suffers injury from a breach may claim compensation, and proof of actual damage or loss remains a sine qua non for compensation of the same.


For a party claiming losses under Section 73, the evidentiary value of primary, contemporaneous records is of paramount importance—without credible proof of actual loss, a claim cannot succeed merely because a breach occurred. Likewise, mathematical models such as Hudson’s formula and normative percentages in the Ministry of Road Transport and Highways (MoRTH) Standard Data Book are merely quantification tools—they cannot operate in an evidentiary vacuum without primary proof that financial loss was genuinely incurred. An arbitral award founded on conjectures, unverified assumptions, or mechanical formula application suffers from perversity and patent illegality, rendering it liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.


Before examining individual sub-claims, tribunals apply two overarching statutory rules: only the injured/aggrieved party who suffers from a breach can claim compensation (a party in breach or responsible for an illegal termination cannot profit from its own wrong), and compensation cannot become a windfall where no actual loss is proved.


Section 73.

Section 73 of the Indian Contract Act, 1872 provides:

“When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it...”

For any party claiming losses under Section 73, evidentiary value is of great importance:

  • Burden of proof on the claimant: The claimant must prove the breach and the actual  loss suffered, rather than mere allegations based on speculation and unfounded evidence. Moreover, Section 73 extends relief to "the party who suffers by such breach," a party found to be in breach itself—or responsible for an illegal termination—cannot take advantage of its own wrong to claim loss of profits flowing from its own breach or wrongful repudiation.

Section 74

For a Compensation for breach of contract where penalty is stipulated, Section 74 of the Indian Contract Act, 1872 provides thus:

“When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.”

Where a contract stipulates liquidated damages (a genuine pre-estimate of loss fixed by the parties in case of breach), the party complaining of the breach has a right to recover reasonable compensation not exceeding the stipulated sum. However, as established in Kailash Nath Associates v. Delhi Development Authority & Anr., (2015) 4 SCC 136, the stipulated sum is a ceiling (upper limit), not an automatic windfall: if actual damage or loss is capable of proof, proof is not dispensed with, and where no loss or damage is suffered at all, the law does not award a windfall. It held that proof of actual damage or loss cannot be dispensed with wherever it is capable of being proved.

In the celebrated landmark judgment of Batliboi Environmental Engineers Ltd. v. Hindustan Petroleum Corporation Ltd. & Anr., (2024) 2 SCC 375, the Supreme Court held that computation of delay damages cannot be whimsical or disingenuous and the same cannot be awarded mechanically using formulas (such as Hudson’s, Emden’s, or Eichleay’s) without credible proof of actual loss or missed business opportunities. 

“16. This is without doubt, a sound legal and correct proposition. However, the computation of damages should not be whimsical and absurd resulting in a windfall and bounty for one party at the expense of the other. The computation of damages should not be disingenuous. The damages should commensurate with the loss sustained. In a claim for loss on account of delay in work attributable to the employer, the contractor is entitled to the loss sustained by the breach of contract to the extent and so far as money can compensate. The party should be placed in the same situation, with the damages, as if the contract had been performed. The principle is that the sum of money awarded to the party who has suffered the injury, should be the same quantum as s/he would have earned or made, if s/he had not sustained the wrong for which s/he is getting compensated.”


Evidentiary Requirements to prove actual loss. 

Compensation for claims like loss of plant and machinery on account of prolongation, idling charges, overheads, loss of profits or opportunity must actually be proved by credible evidence. Let us discuss what kind of evidentiary threshold is required to prove the same.


Loss of Plant and Machinery (Prolongation and Idling Charges)

For proving claims under this head, the claimant must prove that it is the aggrieved party rather than the party in breach, that specific machinery and equipment were physically stationed at the project site during the extended or idle period, were prevented from being demobilized or deployed elsewhere, and actually incurred ownership, hire, or maintenance expenditure. Mere reliance on MoRTH Data Book equipment hire rates without site deployment records is insufficient.

Required contemporaneous evidence:

  • Equipment hire agreements, lease contracts, and machine rental bills/invoices.
  • Daily machinery logbooks, site deployment registers, and joint measurement/hindrance records verifying idle hours or prolonged deployment.
  • Diesel/fuel consumption slips, maintenance/repair bills, and operator wage sheets tied to the specific machinery at site.
  • Proof of actual opportunity cost or inability to demobilize equipment.

In Union of India through Executive Engineer Lucknow Central Division No. 2 v. ANS Construction Ltd., 2024 SCC OnLine Del 4754, the High Court of Delhi set aside an award granting idling compensation where no actual evidence of loss was led:

“65. In the present case, no evidence whatsoever has been produced by the respondent; rather its own Letter speaks to the contrary. When there is no evidence whatsoever led by the respondent of there being any loss, then it cannot be held entitled to any compensation in terms of Sections 73 and 74 of the Contract Act. Such has also been observed in the case of Kailash Nath Associates (supra), which is relied in the case of Edifice Developers Project Engineers Ltd. v. Essar Projects (India) Ltd., (2013) 2 AIR Bom R 244 and also referred to in the case of Ajay Singh (Sunny Deol) v. Suneel Darshan,, 2015 SCC OnLine Bom 1412.

66. It is, therefore, held that the grant of compensation on account of idling of resources, is not only arbitrary but is also contrary to law and not based on any evidence and is perverse. It suffers from patent illegality and is, therefore, liable to be set-aside…’”

Likewise, in Shivalaya Construction Company Pvt. Ltd. v. Delhi Development Authority, 2021 SCC OnLine Del 530, the High Court of Delhi upheld the rejection of machinery underutilization claims founded solely on MoRTH Standard Data Book rates:

“40. It is apparent that the said claims were made on a notional basis. The Arbitral Tribunal rightly rejected the said claims on the ground that SCCPL was unable to substantiate the same. SCCPL’s loss of profit was based on an assumption that it would have earned a profit of 10% and would have incurred overheads of 50%, however, there was no material to substantiate the same. Similarly, SCCPL’s claim for underutilization of machinery and tools was based on rates provided in the Ministry of Road Transport and Highways (MORTH) Standard Data Book and not on the basis of any actual evidence as to the opportunity cost incurred by it.”

Loss of Overheads.

For claims under this head, the contractor must establish that actual, unrecovered overhead expenditure—whether site-specific establishment costs or proportionate head office expenses—was incurred during the extended contract period due to the employer's delay. 

Required contemporaneous evidence:

  • Site payroll registers, salary slips, and provident fund/ESI records for supervisory, engineering, and administrative staff retained during prolongation.
  • Rent receipts for site offices, staff accommodation, and storage yards, alongside electricity, water, and communication bills.
  • Bank guarantee and performance security extension charges, insurance renewal invoices, and GST/tax payment receipts or ledgers demonstrating actual unrecovered outgoings.
  • Audited profit and loss accounts, balance sheets, and chartered accountant certificates isolating project-specific overhead expenditure.


Claim for Loss of Profit.

The evidentiary threshold for establishing a claim for loss of profit is exceedingly high. First, under Section 73 of the Indian Contract Act, 1872, the claimant must be the aggrieved party who suffered from the other party's breach—if the claimant itself was in breach or had illegally terminated the contract, it cannot take advantage of its own wrong to claim loss of profits arising out of its own breach and illegal termination. Second, even where breach by the counterparty is established, the claimant must prove that it actually suffered loss or damage beyond the mere act of breach. Loss of profit must be substantially proved with cogent material; failing substantial proof, the claim is inadmissible because the tribunal cannot justify awarding it.

Required contemporaneous evidence:

  • Proof that the claimant was not in breach and did not wrongfully repudiate or illegally terminate the contract.
  • Original tender bid calculations, rate analysis sheets, and price schedules showing the profit margin factored into the contract price.
  • Audited financial statements and tax returns demonstrating the contractor’s historical net profit margins on comparable projects.
  • Cost-to-completion records and certified running account (RA) bills proving how delay or scope curtailment eroded the anticipated profit margin.


In Batliboi Environmental Engineers Ltd. v. Hindustan Petroleum Corporation Ltd. & Anr., (2024) 2 SCC 375 (supra), the Supreme Court emphasized that loss of profit claims must reflect what the injured party would realistically have earned had the contract been performed, without creating a windfall.

The Supreme Court in Bharat Coking Coal Ltd vs L.K. Ahuja 2004 5 SCC 109 held that:

“It is not unusual for the contractors to claim loss of profit arising out of diminution in turn over on account of delay in the matter of completion of the work. What he should establish in such a situation is that had he received the amount due under the contract, he could have utilised the same for some other business in which he could have earned profit. Unless such a plea is raised and established, claim for loss of profits could not have been granted. In this case, no such material is available on record. In the absence of any evidence, the arbitrator could not have awarded the same. This aspect was very well settled in Sunleyn (B) & Co. Ltd. vs. Cunard White Star Ltd., [1940] 1 K.B. 740, by the Court of Appeal in England. Therefore, we have no hesitation in deleting a sum of Rs. 6,00,000/- awarded to the claimant.” 

In Shivalaya Construction Company Pvt. Ltd. v. Delhi Development Authority, 2021 SCC OnLine Del 530, the High Court of Delhi rejected an assumed 10% profit claim unsupported by financial material:

“40. It is apparent that the said claims were made on a notional basis. The Arbitral Tribunal rightly rejected the said claims on the ground that SCCPL was unable to substantiate the same. SCCPL’s loss of profit was based on an assumption that it would have earned a profit of 10% and would have incurred overheads of 50%, however, there was no material to substantiate the same.”

Similarly in NHAI v. Bumi Hiway (M) Sdn. Bhd., O.M.P. No. 249/2013, the High Court of Delhi held that awarding loss of profit by mechanically applying a formula to the total project cost—when no prima facie evidence of actual loss exists—is contrary to law.


Claim for Loss of Opportunity

Loss of opportunity arises when prolonged retention on a delayed project ties up the contractor’s finite resources—such as specialized plant and machinery, working capital, bank guarantee limits, or key technical personnel—thereby preventing the contractor from bidding for or executing other profitable projects in the market. 

Required contemporaneous evidence:

  • Specific tender notices, invitations to bid, or pipeline projects active during the prolongation window that the contractor was qualified to execute.
  • Proof of actual tender rejections, disqualifications due to exhausted bid capacity, or formal decisions declining tenders because equipment/staff were locked at the delayed site.
  • Machinery and personnel deployment schedules showing limited specialized equipment that could not be duplicated for parallel projects.
  • Bank credit and bank guarantee utilization statements showing exhausted financial limits caused by extended guarantees on the delayed project.

In the landmark judgment of  Unibros v. All India Radio, 2023 SCC OnLine SC 1366, the Supreme Court upheld the setting aside of an award that granted loss of profit/opportunity using Hudson’s formula over a 42.5-month delay without independent evidence of missed tendering opportunities. The relevant para reads as thus:

“17. One might ask, what would be the nature and quality of such evidence? In our opinion, it will be contingent upon the facts and circumstances of each case. However, it may generally include independent contemporaneous evidence such as other potential projects that the contractor had in the pipeline that could have been undertaken if not for the delays, the total number of tendering opportunities that the contractor received and declined owing to the prolongation of the [work]… While this list is not exhaustive and may include any other piece of evidence that the court may find relevant, what is cut and dried is that in adjudging a claim towards loss of profits, the court may not make a guess in the dark; the credibility of the evidence, therefore, is the evidence of the credibility of such.”


The Supreme court in Unibros(supra at para 19) clearly held that a claim for loss of profit, profitability or opportunities only succeeds if the contractor established four conditions i.e 

  1. there was a delay in the completion of the contract
  2. such delay is not attributable to the claimant;
  3. the claimant’s status as an established contractor, handling substantial projects;
  4. credible evidence to substantiate the claim of loss of profitability


MORTH Standard Data Book or any other Formulas to calculate loss cannot be applied in Vacuum.

In arbitration disputes, the Contractor usually, without producing any credible proof of actual loss suffered tends to base its claims solely on the basis of MoRTH standard data book or other formulas like Hudson or emden to quantify its loss. However, such a formula cannot be applied in vacuum without actual proof of loss. 

In M/s Unibros v. All India Radio (2023 SCC Online SC 1366), the Supreme Court while deciding whether Hudson formula can be applied to quantify loss it opined that “While these formulae are helpful when needed, they alone cannot prove the contractor’s loss of profit. They are useful in assessing losses, but only if the contractor has shown with evidence the loss of profits and opportunities it suffered owing to the prolongation.”

In NHAI v. M.G. Contractors Pvt. Ltd., 2025 DHC 5397, the High Court of Delhi set aside an award of Rs. 3.60 crores toward overhead compensation that had been calculated using standard percentages from the MoRTH Standard Data Book without proof of actual overhead spending:

“72........ The standard formulas such as Hudson are essentially tools for computing the extent of overheads/profit, but even while using these formulas, the Arbitral Tribunal or the Courts must ensure that as a matter of fact, the party suffering from the breach has incurred expenditure on overheads attributable to the works executed during the extended period. In other words, the party must lead credible evidence to prove the loss and the standard formulas cannot be applied in vacuum..”

Similarly, in NHAI v. Bumi Hiway (M) Sdn. Bhd., O.M.P. No. 249/2013, the High Court of Delhi invalidated an award granting overheads and profits solely through formulaic multiplication of project cost:

“23. For the aforementioned reasons, the Court is unable to sustain the impugned Award of the Arbitrator as it has proceeded merely on surmises and conjectures in awarding BHSB's claim for overheads and loss of profits without there being any evidence whatsoever produced to even prima facie show that it had suffered overhead charges and incurred losses. This is not a case of inadequacy of evidence but there being no evidence whatsoever to justify the impugned Award. In such circumstances, merely applying formulae to the total cost of the project to calculate the compensation was impermissible in law…”


Practical Aspects to keep in Check

Thus while raising a claim in arbitration, the party raising the same must minutely scrutinize the evidentiary threshold for each sub-claims in order to succeed. Some checklist are given as follows:

  • Explicitly plead and prove that the respondent was in breach and that the claimant was not the defaulting or wrongfully terminating party.
  • Link specific critical-path delay events (with correspondence letters, emails and register entries etc) to each period for which prolongation or idling damages are claimed.
  • Plead and annex contemporaneous contractual notices putting the employer on notice of idling resources, extended overheads, and intent to claim compensation.
  • Segregate claims clearly so that items compensated under price escalation, variation orders, or rate revisions are not duplicated inside prolongation claims.
  • Documentary evidence: Produce actual bills, rent receipts, log books, hire invoice, fuel invoices, tender rejection notices etc.
  • Lead primary accounting witnesses: Examine the Project Manager (to prove physical deployment and hindrances) alongside the Chief Accountant or Statutory Auditor (to prove books of account, vouchers, and tax/GST records).

Conclusion

The Indian arbitration jurisprudence draws a sharp line between identifying a legal wrong and proving a compensable financial claim with credible proof of actual loss suffered. The common claims like loss of plant and machinery, overhead , loss of profits and opportunity as discussed in the aforesaid require great evidentiary threshold which the Arbitral Tribunal heavily weighs on before awarding any of such claims. 

For parties to win these claims and overcome judicial scrutiny requires building an unbroken evidentiary chain during the performance of the contract itself. This can be done by being diligent during performance of work and recording contemporaneous hindrance logs, hire invoices, payroll and bank guarantee records, audited financial ledgers, and concrete tender documentation. When every monetary claim for compensation, especially in the aforesaid common claims is recorded in verifiable contemporaneous evidence  rather than mere arithmetic speculation on the basis of standard data book or formulas, an arbitral award stands on firm legal ground.


Comments

Popular posts from this blog

THE PRACTICE OF EXHIBITION OF DOCUMENTS UNDER THE INDIAN LAW.

WHAT IS 'QUESTION OF LAW' & ' SUBSTANTIAL QUESTION OF LAW'

ARE SUBSIDARIES INCLUDED AS ASSETS OF THE PARENT COMPANY DURING INSOLVENCY.